Kanban metrics that matter: cycle time, throughput and WIP

You do not need a dashboard to improve. But four numbers, measured roughly, tell you most of what you need to know about how work flows.

The four numbers

  • Lead time – from when a card is created (requested) to when it is done.
  • Cycle time – from when work actually starts to when it is done.
  • Throughput – how many cards are finished per week.
  • Work in progress – how many cards are started but not finished right now.

Teams define the exact start and end points slightly differently. Pick a definition and stick to it; consistency matters more than precision.

How they connect

Little’s Law, from queueing theory, links them: average cycle time = average WIP ÷ average throughput. If you finish 5 cards a week and have 10 in progress, cards take about 2 weeks on average. Want faster? Either finish more per week (hard) or have less in progress (easy, and usually also raises throughput because there is less switching).

Measuring without a spreadsheet

  • Throughput: filter for cards closed in the last week. Count them. Do this each Friday.
  • WIP: count the cards in your active columns. CBSE.CLUB shows the count on each column.
  • Cycle time: open a few recently closed cards; their history shows when they moved into progress and when they closed.

Write the three numbers in a recurring card or a team note each week. After a month you will see trends.

Cumulative flow diagrams

A cumulative flow diagram plots how many cards were in each stage over time. Widening bands mean work is piling up. They are useful for larger teams; small teams can usually see the same thing by glancing at the board.

Metrics to avoid

  • Cards closed per person. It encourages splitting work into tiny cards and discourages helping others.
  • Velocity across teams. Estimates are not comparable between teams.
  • Utilisation. Keeping everyone 100% busy creates queues. Some slack is what makes flow possible.

Using metrics well

Look at them together, as a team, as a starting point for conversation: “Cycle time went up. What happened?” Never as a target for individuals. The moment a measure becomes a target, people optimise the number instead of the work.

Frequently asked questions

What is the difference between lead time and cycle time?

Lead time runs from when work is requested to when it is delivered. Cycle time runs from when work starts to when it is delivered. Lead time includes waiting in the backlog.

What is throughput in kanban?

The number of work items finished in a period, usually per week.

What is Little’s Law?

A result from queueing theory: average time in a system equals average number of items in it divided by average throughput. In kanban, cycle time = WIP ÷ throughput.