Throughput

The number of work items a team finishes in a given period, such as cards closed per week.

Throughput is a simple count of finished work over time. Unlike velocity, it needs no estimates.

Measuring it

Count cards closed each week. In CBSE.CLUB, filter by “closed in the last week”.

Forecasting with it

If you close 6–8 cards a week and have 30 cards planned, you will likely need 4–5 weeks. Simple, and usually more accurate than story points.